Public Works

Construction Updates

For a current list of expected lane closures see the Texas Department of Transportation's Highway Conditions Search Tool.

Information about local construction projects is available online from the Texas Department of Transportation. Midtown Express Project information is available at drivemidtown.com and the project's Closures and Traffic Changes for Euless can be found under the section SH 183 – SH 121 to Esters Road.

May 2016

STREET/STREAM REPAIR AND RECONSTRUCTION

Public Works crews continue cleaning and clearing debris from the creeks, drainage liners, drain inlets, and the storm sewer system due to the recent rain events.

Public Works street crews continue crack sealing and repairing pot holes on various streets around town. They are also making asphalt spot repairs on the streets that are due for asphalt overlay in the spring.

Contractor Total Highway Maintenance has completed the application of HFST (High Friction Surface Treatment) on the east bound lanes of W. Pipeline Rd. between Wade and Driftwood Dr. All short term and intermediate recommendations from the February 2016 Kimley Horn study have been completed except the Warrant Study at Wade & Pipeline.

Viking Construction began Micro-Sealing (Slurry Seal) early last week. The project includes sections of 31 streets. Work was completed on April 27th.

Reynolds Asphalt was scheduled to start street milling & overlay on May 2. However, due to weather issues, the work has been delayed until early June. The project includes sections of 13 streets. The work will take several weeks to complete.

WATER METER REPLACEMENT PROJECT

The Water Meter Replacement Project is proceeding forward. Crews have installed the network infrastructure. Meter installation crews began preparing the existing meter boxes for the meter swap-outs. Meter installations are planned to begin May 2nd.

RECLAIMED WATER PHASE 2

Bids were opened on November 18th.and City Council awarded the project to Circle C Construction on November 24th. Construction began on January 18th and is progressing on Bear Creek Pkwy. and Ash Lane.

MIDTOWN EXPRESS (SH 183)

Utility package bids were opened March 15. Utility work is expected to begin in May. The contractor continues working at the interchanges of 157 & 183 and Ector Dr & 183.

FY 2015-16 SANITARY SEWER REHAB

City Council awarded the project to Circle C Construction on November 10th and construction began on January 4th. Work is complete on Town Creek, Glenn Drive, and Crane Drive. Construction is progressing for areas along Pipeline Road.

FY 2015-16 WATER REPLACEMENT PROJECT

The FY 2015-16 Water Replacement Project consisting of 1,200 feet of replacement pipe was presented to City Council on April 26th. Minor construction will take place on Shelmar Dr. and Donley Dr. in one day with site restoration occurring over the subsequent several days. This will take place in early May.

Project Updates

You can sign up to receive email updates for construction projects via MyEuless.