Public Works

Construction Updates

For a current list of expected lane closures see the Texas Department of Transportation's Highway Conditions Search Tool.

Information about local construction projects, including the North Tarrant Express projects, is available from the Texas Department of Transportation.

March 2015

STREET CONSTRUCTION PROJECTS

BRAZOS BOULEVARD CONSTRUCTION

Brazos Boulevard is a new 37 foot wide curb and gutter street that is under construction from Red River Drive to Rio Grande Boulevard.

Construction began on July 16, 2014 and is expected to be completed by mid-February.  Construction is approximately 99% complete.
CULLUM DRIVE RECONSTRUCTION

Cullum Drive is being reconstructed from SH 10 to East Huitt Lane.  The street improvements will upgrade this portion of the roadway from a two lane county road type section with open drainage to a standard curb and gutter street section with underground drainage systems.

City Council awarded the contract to McClendon Construction of Burleson, Texas.  Construction began on January 20, 2014 and was scheduled to be completed in October, 2014.  Project to be completed in March.

Currently, the contractor has completed the street paving, driveway entrances and sidewalks.  The contractor will be completing the “punch list” in March.  Several sections of sidewalk were replaced in January and February to meet Americans with Disabilities Act (ADA) compliance.

RUTH MILLICAN COMMUNITY CENTER PARKING LOT

During the Cullum Drive reconstruction project, the Euless Public Works Streets Department replaced a strip of deteriorating asphalt approximately 100’ long x 8‘ wide along the south edge of the parking lot, this parking area had become unstable due to large tree roots growing under the asphalt. At the same time a new parking area was added at the rear of the Community Center, this new area is approximately 90 feet by 60 feet. Also, a new concrete transition was poured between the parking lot and the existing Community Center sign. In addition recently a contractor seal coated the entire parking lot.  Lot was also recently re-striped by City crews.

RIO GRANDE BOULEVARD CONSTRUCTION

The project will construct approximately 2,970 linear feet of the Rio Grande Boulevard extension to Cheek-Sparger Road. Two side streets will connect the southbound SH 121 frontage road with Rio Grande Boulevard. The southbound SH 121 frontage road will be widened to accommodate the entrances to the side streets. The project will complete the bridge over Little Bear Creek, provide landscaping and irrigation to the medians, and construct entry features along the southbound SH 121 entry connections and Cheek-Sparger Road.

TARRANT COUNTY CDBG ACCESSIBILITY RAMPS AND SIDEWALKS PROJECT

All ramps have been completed. Final inspection was conducted and one stretch of sidewalk at Main & Edinborough is being re-worked.

SANITARY SEWER LINE REPLACEMENT PROJECT

FY 14-15 SANITARY SEWER REHABILITATION PROJECT

Contract was awarded by Mayor and Council August 26, 2014 to Circle C Construction. 

This project consists of rehabilitation of sewer lines servicing the following areas:

  • Denton Drive between Collins Drive and Harwood Road; to include portion of Bell Drive
  • Dallas Drive between Denton Drive and Irion Drive
  • Irion Drive between Dallas Drive and Harwood Road
  • Construction began on October 6, 2014 and should be completed in March.

Project Updates

You can sign up to receive email updates for construction projects via MyEuless.