Public Works

Construction Updates

For a current list of expected lane closures see the Texas Department of Transportation's Highway Conditions Search Tool.

Information about local construction projects is available online from the Texas Department of Transportation. NTE TEXpress Toll Lane information is also available.

April 2015

STREET CONSTRUCTION PROJECTS

BRAZOS BOULEVARD CONSTRUCTION

Brazos Boulevard is a new 37 foot wide curb and gutter street that is under construction from Red River Drive to Rio Grande Boulevard.

Construction began on July 16, 2014 and is complete.

CULLUM DRIVE RECONSTRUCTION

Cullum Drive is being reconstructed from SH 10 to East Huitt Lane.  The street improvements will upgrade this portion of the roadway from a two lane county road type section with open drainage to a standard curb and gutter street section with underground drainage systems.

City Council awarded the contract to McClendon Construction of Burleson, Texas.  Construction began on January 20, 2014 and was scheduled to be completed in October, 2014.  Project is complete.

RUTH MILLICAN COMMUNITY CENTER PARKING LOT

During the Cullum Drive reconstruction project, the Euless Public Works Streets Department replaced a strip of deteriorating asphalt approximately 100’ long x 8‘ wide along the south edge of the parking lot, this parking area had become unstable due to large tree roots growing under the asphalt. At the same time a new parking area was added at the rear of the Community Center, this new area is approximately 90 feet by 60 feet. Also, a new concrete transition was poured between the parking lot and the existing Community Center sign. In addition recently a contractor seal coated the entire parking lot.  Lot was also recently re-striped by City crews.

STREET REPAIR AND RECONSTRUCTION

Signet Drive from Lois Lane to Hwy 157 was reconstructed, the subgrade base material was stabilized and a new 2” layer of asphalt was then placed and finished by the Euless Public Works Streets Department. The new surface is now ready for pavement striping.

Kynette Street from Wilshire Drive to Crowe Drive was also reconstructed, the subgrade base material was stabilized and a new 2” layer of asphalt was then placed and finished by the Euless Public works Streets Department. The new surface is now ready for pavement striping.

TARRANT COUNTY CDBG ACCESSIBILITY RAMPS AND SIDEWALKS PROJECT

The project has received final acceptance from Tarrant County. The two year maintenance period began on February 25, 2015.

HARWOOD ROAD SIDEWALK

A new sidewalk has been constructed along the north side of W Harwood Road near the QuikTrip Service Station at the corner of W Harwood and Hwy 157. The new sidewalk fills in a gap and connects the existing sidewalks coming from Hwy 157 and from Timber Ridge Ct. Project is complete.

SANITARY SEWER LINE REPLACEMENT PROJECT

FY 14-15 SANITARY SEWER REHABILITATION PROJECT

Contract was awarded by Mayor and Council August 26, 2014 to Circle C Construction. 

This project consists of rehabilitation of sewer lines servicing the following areas:

  • Denton Drive between Collins Drive and Harwood Road; to include portion of Bell Drive
  • Dallas Drive between Denton Drive and Irion Drive
  • Irion Drive between Dallas Drive and Harwood Road
  • Construction began on October 6, 2014 and is complete.

WATER SYSTEM PROJECTS

WATER MAIN VALVE MAINTENANCE

The valve maintenance crew exercised 44 water main valves in March. Since the start of the valve exercising program began in October, a total of 514 valves have been exercised.

LEAK DETECTION PROGRAM

The leak detection program is in the process of being awarded to Samco. Their crews should start the water main leak detection and assessment survey in the next few weeks.

SCADA PROJECT

All well sites have been equipped with SCADA and are waiting final testing to begin startup. Several items are being worked out at the Reclaimed Pump Station and a chlorine analyzer will be installed at the 2700 N Main Elevated Storage Tank next week. The chlorine rooms at two of the well sites are being upgraded. The project is expected to be completed by the end of April.

Project Updates

You can sign up to receive email updates for construction projects via MyEuless.